The most productive semiconductor plant worldwide
AMD Fab 36 in Dresden, Germany, 2005
“The punctual opening of AMD Fab 36 in Dresden is another success story. This was another success in the record series of excellent results based on our production strategies and goals.” This statement by Hector Ruiz, CEO of AMD is also an expression of the high level of satisfaction with his General Contractor for the construction of the “Fab 36”, a high-performance plant for 300 mm wafers.
Client: Advanced Micro Devices, Inc. (AMD)
Service scope: General Contractor for consultation, planning and construction, equipment and process support; in parallel turnkey construction of energy supply centre EVC II
Key data:
- Order volume 380 million euros
- 14,500 m² cleanroom area
Construction time: 24 months
Special features:
- Production at the directly adjacent AMD Fab 30 has to continue uninterrupted and could not be compromised by construction work at Fab 36.
|